New composite coupler at Schwandorf substation

For the construction of a new interconnected coupler at the Schwandorf substation, several units were replaced and supplemented in the vicinity of the old 380 kV outdoor switchgear, requiring new individual foundations for lightning protection masts, overhead conductors and single-column disconnectors.

A permanent pile foundation was required due to the geological conditions. The micropiles installed are effective as a permanent foundation for the foundations.

A total of 156 micropiles with a total length of 1092 metres were used for the foundations.

Services performed by ANP-ES:
– Pile testing in accordance with DIN 14199

Client:
TenneT TSO GmbH
Bernecker Str. 70
95448 Bayreuth
GERMANY

Planning:
GSGE GmbH
Gewerbe Str. 15
83355 Grabenstätt
GERMANY

Execution:
Franz Kassecker GmbH
Egerer Str. 36
95652 Waldsassen
GERMANY